Ore Bridge Demolition
Demolition, Infrastructure
- Removal of of 520′ Ore Bridge through implosion due to it’s compromised status.
- The Ore Bridge was suspended 120′ in the air over the top of an active conveyor systems that fed iron ore to a blast furnace that had to remain operation during the entire project.
- 80lf of the bridge was rigged to and cut in multiple sections then lowered to the ground to ensure the conveyor would not be compromised during the blast. Remaining bridge was loaded with explosives and imploded.”